Safety first
Before drilling, check both sides of the wall and consider where electrical, water and gas services may run. Detection tools are helpful but imperfect. Use a stable ladder or platform, wear suitable eye and hearing protection, and control dust. If the wall construction or service location is uncertain, stop and engage an appropriately qualified person.
Before you begin
This guide begins after you have selected your Gallery System. Use the Gallery System calculator to confirm track quantities and the Gallery System product guide for hanger, hook and load compatibility.
Gallery Systems’ published instructions provide the installation sequence. The Shakespeare Solutions field notes throughout this guide add practical detail learned from installing the system on a wide range of Australian walls.
Tools and protective equipment
- Tape measure, pencil and marker
- Stud finder suited to the wall
- Spirit or laser level
- Drill and material-appropriate bits
- 4 mm metal bit for the track
- Driver or screwdriver
- 24 TPI or finer hacksaw and a mitre box
- Drop saw with an aluminium blade, if preferred
- Metal file
- Hammer and, if required, a clean plastic mallet
- Stable ladder or work platform
- Vacuum or dust extraction
- Eye and hearing protection plus suitable respiratory protection
Working practically: the track is supplied without fixing holes so it can be drilled to suit the wall. A two-metre track can usually be managed by one confident person; a second pair of hands is particularly useful with three-metre lengths and longer runs.
1. Plan the track position and access
The Gallery System track is larger than Slimline and is screwed directly to the wall through the upper channel of its H-shaped profile. Check every wall before drilling and plan both the finished position and how hangers will enter the track.
- Straight corniceThe track can be installed directly beneath it when the drill can reach the upper fixing channel without damaging the cornice.
- Square-set ceilingUsually sit the track down slightly. The fixing hole is drilled through the top of the track, making it difficult to hold a drill square when the track is tight against the ceiling.
- Very high ceilingConsider keeping the track lower so it remains accessible from a normal stepladder. About 2.6 metres from the floor is often a sensible height.
- Strong architectural lineA door head or former picture-rail height can provide a considered alternative.
- Clear Tape hangersLeave an accessible track end or a loading gap of at least 40 mm where hangers can be added and removed without sliding them several metres along a long run.
If Gallery Lighting may be added later: install a continuous track run, leave a 40 mm gap at corners, keep the track no higher than approximately 2.6 metres and allow at least 15 mm below the ceiling or cornice so lighting wands can be fitted and removed. Power is introduced through a junction box; a section of track can be cut out for it when the lighting is installed.
Clear Tape needs end access. Stainless-steel cable and Clearline hangers use a removable track slide and can be inserted at any point, so loading gaps are not required for those hanger types.
2. Drill and set out each track length
Gallery Systems instruction
Use the V-groove in the top of the track as the drilling guide. The manufacturer specifies at least five fixings per two-metre length, with holes near each end and the remaining holes approximately 400-500 mm apart. Read the Gallery System Track instructions (PDF).
Shakespeare Solutions field notes
Use five fixings for a two-metre track and seven for a three-metre track. We almost always include a centre fixing, even when it does not coincide with a stud, because it balances the track while the remaining positions are marked and makes the length easier to install and remove.
- Locate the practical studs. Mark the stud positions, then place the track against the wall and transfer those positions onto its upper V-groove.
- Plan the full fixing pattern. Include the centre hole, keep the end holes at least 20 mm from the ends and add intermediate positions so the track is supported evenly.
- Drill the track. Use a 4 mm metal bit for the supplied 8-gauge screws. Support the track securely and remove any burrs that could stop it sitting flat.
- Use the centre fixing first. Hold the track at the selected height, fix or temporarily support it at the centre, align it and mark the remaining holes on the wall.
- Remove the track. Prepare the remaining wall fixings using the appropriate method in Step 3, then return the track for final installation.

Do not force every fixing onto a stud. Prioritise every practical stud, then use a suitable hollow-wall fixing where the planned pattern falls between studs.
3. Prepare fixings for the wall type
Gallery Systems instruction
The manufacturer illustrates direct fixing into studs, Wallmate-style plasterboard fittings and masonry plugs. See the manufacturer’s fixing sequence (PDF).
Shakespeare Solutions field notes
First assess the substrate—the type of wall you are working on—then prepare each marked position. Plasterboard on timber or steel studs and solid masonry are the two most common constructions.
Plasterboard walls
Timber studs: fix the track directly with the supplied 8-gauge screw. Where no stud is available, use a suitable Wallmate, toggle or other plasterboard fixing.
Installing a Wallmate accurately: start with a small pilot hole to confirm that no stud is present, then use a drill bit approximately the same width as the Wallmate’s cutting tip to form an accurately centred opening before driving it.
Steel studs: a StudBuddy magnetic stud finder is particularly useful. Start with a 2 mm pilot, enlarge it to a 3 mm hole, then drive the 8-gauge screw. Carry spare 2 mm bits on longer installations.
Fire-rated or acoustic board: nylon Wallmates can crack in harder boards. Use a zinc Wallmate or another fixing approved for the substrate; we often use TOX Deco 6/41 all-purpose wall plugs.
Square-set plasterboard: pressed-metal corner bead can prevent a Wallmate passing through near the ceiling. Sit the track down where practical, or drill an accurate opening and use a TOX Deco 6/41 plug.
Masonry and brick walls
Use a rotary hammer with a suitable SDS masonry bit and hold dust extraction beneath the hole. A four-point bit tends to wander less.
For a TOX Deco 6/41 plug, we normally drill a 5.5 mm wall hole. A standard red Star Plug normally uses a 6 mm hole. Follow the fixing manufacturer’s current screw, diameter and embedment specifications.
Start smaller in friable old brick or unstable render and enlarge carefully. If a plug spins in an isolated powdery hole, we will often use hot-melt glue to hold it while the screw expands the plug. If it happens repeatedly, reduce the drilled-hole diameter or reconsider the fixing method.
Other wall surfaces
Lath and plaster: do not drive a Wallmate into this brittle material. Drill slowly and fix into sound timber lath where possible. If a required position passes through a gap, carefully enlarge the opening and use a TOX Deco 6/41 plug, recognising that the available capacity is less certain.
Tiled surfaces: pass through the tile slowly with a tile-appropriate diamond bit or hole saw, then identify and fix to the substrate behind it rather than treating the tile as structural.
4. Cut, install and join the track
Gallery Systems instruction
The manufacturer supplies the track undrilled so fixing positions can be matched to the wall. Refer to the Gallery System Track instructions (PDF).
Shakespeare Solutions field notes
Work progressively. Measure for ordering, but mark final cuts against the actual wall as the installation proceeds.
- Mark the fitted length. At a perpendicular wall, reverse the track against the wall and transfer the cut position, allowing about 1 mm tolerance unless a planned loading or lighting gap is required.
- Make a cool cut. Support the track in a mitre box and use a 24 TPI or finer hacksaw, or clamp it securely and use a drop saw fitted with an aluminium blade.
- True the end. Remove burrs with a metal file. Factory ends can be joined as supplied, but removing approximately 0.5-1 mm or carefully filing away the powder coating can produce a cleaner, squarer joint.
- Fix the first length. Start with the centre fixing, confirm the track is correctly aligned and then secure the remaining positions, taking care not to distort the H-shaped profile.
- Join the next length. Insert a Gallery System Track Joiner into the first length, position the next track, slide the joiner across the junction and tighten its two grub screws.
Joiners are now our usual approach: tracks can be butt-joined without one, but small wall or fixing variations can leave the ends a millimetre or two out of alignment. A joiner keeps the junction neat and true. It also prevents a dropper passing through the join. Stainless-steel cable and Clearline hangers can simply be removed and reinserted on the other side; omit the joiner only when uninterrupted passage is specifically required.
Do not use an abrasive hot saw intended for steel. Use a hacksaw and mitre box or a drop saw with an aluminium blade.
5. Finish corners and track ends
For a picture-hanging-only installation, stop each track at the corner and fit an end cap to the exposed end. At an internal corner, the tracks can finish slightly short rather than being forced into an imperfect junction.
When preserving the 40 mm corner gap for future Gallery Lighting, stop both tracks short and use the lighting system’s internal or external corner cover to conceal the gap and, later, the connecting cable. These covers can also provide a neat corner finish before lighting is added.
Keep the lighting plan consistent around the room. A mixture of tight corners and accessible lighting gaps can make a later retrofit unnecessarily difficult.
6. Add the selected hangers
Gallery Systems instruction
Clear Tape is assembled around its locking capsule and inserted through a track end. Stainless-steel cable and Clearline use a track slide that can be inserted from below at any point. Review the applicable instructions before use: Clear Tape and stainless-steel cable and Clearline.
Hanger installation
Clear Tape
Cut the required tape length, feed it through the capsule to form a loop and swing the locking bar through the loop. The short end of the tape and the locking bar must face the front or the locking action will fail. Pinch the capsule and insert it through an accessible track end.




Assemble the capsule, then load it through a track end.
Stainless-steel cable and Clearline
Feed the hanger through its track slide, tilt the slide into the underside of the track and straighten it so it sits level. Both hanger types are installed in the same way and can be added or removed anywhere along the track.




Tilt the slide into the track, then straighten it.
7. Fit hooks and hang artwork
Gallery Systems instruction
Allen Key Hooks are loosened, positioned and retightened with the supplied key. Push Button Hooks move freely while the button is held and grip when it is released. Check compatibility in the product guide and review the Allen Key Hook and Push Button Hook instructions.
- Single hanging: place one hook beneath the centre of the picture wire.
- Double hanging: use two D-rings or equivalent mounting points. Do not place two hooks on one wire; they can creep towards the centre.
- Use two droppers when approaching a single-dropper limit, when the artwork needs help staying level, for visual balance or where it may occasionally be disturbed.
- Do not add a third dropper to gain capacity. If two correctly rated droppers are insufficient, use another method such as a Z Bar or French cleat.

For a Push Button Hook, feed the matching hanger into the top of the hook, hold the button while setting the height and release it to grip. As a starting point, position the centre of the artwork at approximately the viewer’s eye height, then adjust it to suit the room.

Troubleshooting
The adjoining track ends do not align cleanly
Small differences in the wall or fixing positions can leave butt-joined lengths slightly out of alignment. Fit a Gallery System Track Joiner across the junction to draw the two ends into a neat, consistent line.
Adding Clear Tape hangers requires too much sliding
Clear Tape capsules can enter only through a track end. Use the nearest accessible end or planned loading gap. If Clear Tape will be used regularly on a long run, create practical loading points rather than relying on one distant end.
A dropper cannot pass through a track join
A Track Joiner occupies the inside of the track and prevents droppers passing through. Stainless-steel cable and Clearline hangers can be removed and reinserted on the other side. If uninterrupted Clear Tape movement is essential, that junction must be planned without a joiner.
Manufacturer instructions
Keep the original Gallery Systems sheets with the system for their diagrams and component instructions.
- Gallery System TrackPDF
- Gallery System Clear TapePDF
- Gallery System Stainless Cable and ClearlinePDF
- Gallery System Push Button HookPDF
- Gallery System Allen Key HookPDF
If the wall construction is uncertain or this kind of work is not for you, find an authorised Gallery Systems installer.